1. 
What is the average of 22.46, 34.78, 41.67, 65.45 and 22.98?

2. 
How to calculate area of shop floor?

3. 
No of good products produced in a machine in a shift is 2500, ideal cycle time is 2.5 seconds, planned production time is 420 minutes, What is OEE?

4. 
What is the command for trim tool in Autocad?

5. 
What should be the ultimate aim of an Industrial Engineer?

6. 
In Microsoft Excel, which character starts with a formula?

7. 
A assembly line has 4 operations and it's cycle times are 4.5 sec, 6.7 sec, 5.4 sec and 5.9 sec. What is the output per hour?

8. 
There are two process for a product with cycle times, 2.67 minutes and 4.5 minutes respectively. Manning of each processes are 1 and 2 respectively. Demand of the product is 300 nos per shift. Working time per employee is 420 minutes. Calculate manpower required per shift?

9. 
If you want to provide a drop-down list in a cell of Microsoft excel, which of the following will you choose?

Add description here!

10. 
If you want to get the maximum value from a list of numbers in excel, which function wi you use?

11. 
A assembly line has 4 operations and it's cycle times are 4.5 sec, 6.7 sec, 5.4 sec and 5.9 sec. In line balancing problem what is the line balancing efficiency?

12. 
Meaning of word Kaizen

13. 
If you want to move an object from one place to other in Autocad, which command will you type?

14. 
In Microsoft Excel, if you want to change the colour of a cell according to the values in it, which of the below will you choose?

Add description here!

15. 
4 persons should work together to complete a process on a product. What is the Manning of that process?

16. 
How to turn on ortho mode in Autocad?

17. 
A process of a product requires a machine, demand of the product is 50 nos per day, cycle time of the process is 2.5 minutes, machine runs for 3 shift for 420 minutes each. What is the expected utilization of that machine per day?

18. 
Convert 346 seconds to minutes?

19. 
Suppose there are two columns A and B in Microsoft Excel and if you want to find a value in column B corresponding to value in column A, which function will you use?

20. 
A machine produces 45 products per day, calculate no of days required to complete the work order of 799 products ?

21. 
What we do in standardize phase of 5S?

22. 
What is the 4th phase in 5S methodology?

23. 
Normally which time should be considered for manpower analysis and capacity analysis?

24. 
What is the next step after collecting observed times in a Time Study?

25. 
In a Time Study observed time is 3.45 minutes, rating factor is 120. What is the Normal time?

26. 
Which of the following tool is used for finding root cause of a problem?

27. 
A customer wants 500 products per day. A plant works in 2 shifts and working time per shift is 420 minutes. What is the takt time?

28. 
Normal time is 4.67 minutes, relaxation allowance is 11% and other allowance is 3%. Calculate Standard Time.

29. 
Takt time of a product is 0.5 minutes and the cycle time of a process is 4.25 minutes, calculate no of workstation for that process?

30. 
A person is traveling in a car with an average speed of 45 km/hour. His destination is 159 km away. How time will he take to reach his destination?


Discover more from Know Industrial Engineering

Subscribe to get the latest posts sent to your email.

2 thoughts on “Industrial Engineering Online Exam”

Leave a Reply

Your email address will not be published. Required fields are marked *