Copy Link Button
Share
Top Article Link
Start Chat
Premium Bottom Bar

Industrial Engineering Online Exam

Welcome to Online exam for testing skills of an Industrial Engineering professional

 

1. 
A assembly line has 4 operations and it's cycle times are 4.5 sec, 6.7 sec, 5.4 sec and 5.9 sec. What is the output per hour?

2. 
Meaning of word Kaizen

3. 
What is the command for trim tool in Autocad?

4. 
What should be the ultimate aim of an Industrial Engineer?

5. 
If you want to get the maximum value from a list of numbers in excel, which function wi you use?

6. 
Purpose of line balancing?

7. 
What is the 4th phase in 5S methodology?

8. 
What we do in standardize phase of 5S?

9. 
Normally which time should be considered for manpower analysis and capacity analysis?

10. 
Which of the following tool is used for finding root cause of a problem?

11. 
In Microsoft Excel, which character starts with a formula?

12. 
Takt time of a product is 0.5 minutes and the cycle time of a process is 4.25 minutes, calculate no of workstation for that process?

13. 
Normal time is 4.67 minutes, relaxation allowance is 11% and other allowance is 3%. Calculate Standard Time.

14. 
In a Time Study observed time is 3.45 minutes, rating factor is 120. What is the Normal time?

15. 
If you want to move an object from one place to other in Autocad, which command will you type?

16. 
A process of a product requires a machine, demand of the product is 50 nos per day, cycle time of the process is 2.5 minutes, machine runs for 3 shift for 420 minutes each. What is the expected utilization of that machine per day?

17. 
Convert 346 seconds to minutes?

18. 
A machine produces 45 products per day, calculate no of days required to complete the work order of 799 products ?

19. 
A person is traveling in a car with an average speed of 45 km/hour. His destination is 159 km away. How time will he take to reach his destination?

20. 
A assembly line has 4 operations and it's cycle times are 4.5 sec, 6.7 sec, 5.4 sec and 5.9 sec. In line balancing problem what is the line balancing efficiency?

21. 
How to turn on ortho mode in Autocad?

22. 
In Microsoft Excel, if you want to change the colour of a cell according to the values in it, which of the below will you choose?

Add description here!

23. 
4 persons should work together to complete a process on a product. What is the Manning of that process?

24. 
A customer wants 500 products per day. A plant works in 2 shifts and working time per shift is 420 minutes. What is the takt time?

25. 
Convert 375658 cm square to square feet

26. 
What is the average of 22.46, 34.78, 41.67, 65.45 and 22.98?

27. 
Refer the picture attached. If you want to remove the portion of the horizontal line which is at the right right side of vertical line, which tool will you use in Autocad?

28. 
Two people will be needed to carry a box from one place to other and time required will be 3.7 minutes. What is the man minutes?

29. 
There are two process for a product with cycle times, 2.67 minutes and 4.5 minutes respectively. Manning of each processes are 1 and 2 respectively. Demand of the product is 300 nos per shift. Working time per employee is 420 minutes. Calculate manpower required per shift?

30. 
What is the next step after collecting observed times in a Time Study?


Discover more from Know Industrial Engineering

Subscribe to get the latest posts sent to your email.

2 thoughts on “Industrial Engineering Online Exam”

Leave a Reply

Your email address will not be published. Required fields are marked *