In this article I will explain how to calculate the manpower cost you have saved by implementing some improvements in an operation.
Suppose the present output of an operation is 120 per hour. One manpower is allocated for doing the operation. And you have done some improvement in the operation and increased the hourly output to 145. So increase in the output per hour is 25 nos.
Man minutes required per product before improvement = 60/120
= 0.5
Man minutes required per product after improvement is = 60/145
= 0.4137
Man minutes saved per product = 0.5 – 0.4137 = 0.0863
Suppose the demand of the product per month is 200000.
Man minutes saved per month is 0.0863 x 200000 = 17260
Suppose, hourly cost of the manpower is Rs 100.
Cost for one man minute = 100/60 = Rs. 1.66
So total savings per month = 1.66 x 17260
Which is Rs. 28651/-
Oh my god this may be close to your salary.
Please note that we will actually get this saved money only if we use the saved man minutes for other value adding activities.
We are done with the calculation.
If you want to know more about man minutes please click the link below
If you want to know how to calculate manpower required, please click the link below
For using free online manpower calculator tool please click the link below
Thank you for reading.
If you know any subject that can be related to manufacturing industry or industrial engineering, you can earn some income by becoming article contributor of this website. For knowing more about it, please visit Join us page.
You don’t need to have any experience in article writing, just knowledge on the subject is needed.
Also you can know more about our team of article contributors by visiting the about us page.