Line Balancing – How to do it

Line balancing is done to reduce or eliminate the waiting time in the workstations of an assembly line which runs in one piece flow. Thus we can utilize the resources such as manpower and machinery/equipment more effectively.

Line balancing definition

Line balancing is a method for eliminating idle time in assembly line and also for adapting the line to takt time.

Advertisement

Relationship between bottleneck and Line balancing in manufacturing industry

Before we go to how to do line balancing I recommend you to read the article on Bottleneck in a manufacturing industry. So that you can easily understand this line balancing. In the example explained in the article ‘Bottleneck in a manufacturing industry’, the operators at the work station A, B and D will be waiting, because the cycle time of these work station is lower than workstation C.

Aim of line balancing

So our aim of line balancing is to make the cycle time of all workstation almost same so that there is no waiting. Through line balancing we are eliminating one of the 8 wastes of lean manufacturing.

Also there is another very important aim of line balancing, which is aligning the assembly line according to the demand, by the concept of takt time. Thus we prepare the assembly line for delivering the right quantity according to the demand.

Ok lets start…

How to do line balancing of an assembly line (explained with example)

Let’s balance the assembly line of a toy.

Assembly process have following activities.

Activity 1 : Inspection and flash removal of plastic moulded part 1. Cycle time 1.48 minutes.

Activity 2 : Inspection and flash removal of plastic moulded part 2. Cycle time 1.70 minutes.

Activity 3 : Assembly of part 1 and part 2. Cycle time 0.98 minutes.

Activity 4 : Insertion of screw 1. Cycle time 0.48 minutes.

Activity 5 : Insertion of screw 2. Cycle time 0.50 minutes.

Activity 6 : Insertion of screw 3. Cycle time 0.48 minutes.

Activity 7 : Cleaning. Cycle time 1 minutes.

Activity 8 : Labelling. Cycle time 0.65 minutes.

Activity 9 : Inspection. Cycle time 0.75 minutes.

Activity 10 : Packing. Cycle time 0.9 minutes.

Demand of the toy per day is 240 nos. And the assembly line works in one shift per day. And working time per shift is 420 minutes.

This is the all details.

Now we shall start the calculation.

Takt time calculation

First thing to calculate is takt time. Here takt time is 420/240, which is 1.75 minutes.

And total cycle time is 8.92 minutes (sum of all activities).

Now we can calculate theoretical no of work station, which is total cycle time/takt time.

= 8.92/1.75

= 5.09

Say 6 work stations.

This theoretical work station is just for information. But we can fix it as the minimum no of work station required, which is 6 nos.

No we can allocate the activities to the work stations. But, before that we should know the precedence of each activity. This is usually communicated by precedence table or precedence diagram. Please refer the precedence table below.

Precedence table
ActivityPrecedence Activity
Activity 1
Activity 2 Activity 1
Activity 3 Activity 2
Activity 4 Activity 3
Activity 5 Activity 4
Activity 6 Activity 5
Activity 7 Activity 6
Activity 8 Activity 7
Activity 9 Activity 8
Activity 10 Activity 9
Precedence table in line balancing

Our situation is very simple and it’s good to start with the simple one.

By referring the precedence diagram or table we can know which are the activities to be done before and after an activity.

Ok, now we can allocate the activities to the work station. The most important thing to be noted while allocating activities to work station is, the total cycle time of the work station should not be more than the takt time, which is 1.75 minutes. If its not it will not deliver the desired output which is 240 nos per shift.

Work station 1 : Activity 1, Cycle time is 1.48 minutes.

Work station 2 : Activity 2, Cycle time is 1.70 minutes.

Work station 3 : Activity 3, Cycle time is 0.98 minutes.

Work station 4 : Activity 4 + Activity 5 + Activity 6, Cycle time is 1.46 minutes.

Work station 5 : Activity 7 + Activity 8, Cycle time is 1.65 minutes.

Work station 6 : Activity 9 + Activity 10, Cycle time is 1.65 minutes.

Get KIE Premium to Continue Reading

This article is available exclusively for KIE Premium members. Subscribe to get full access to practical industrial engineering knowledge and in-depth learning resources.

Read every complete KIE Premium article
Instant access after successful payment
Keep Premium access for 365 days

Now or Never

We’ve got your back on your manufacturing journey — Stay in touch

Follow us for step-by-step guidance, templates, and insights that save time and reduce mistakes.

Know Industrial Engineering Platform – Helping manufacturing industry professionals worldwide since 2019

1 thought on “Line Balancing – How to do it”

Leave a Comment

Your email address will not be published. Required fields are marked *