How to Calculate Standard Output of an Assembly Line

In this article I will explain how to calculate standard output of an assembly line. Standard output is the no of products to be produced from an assembly line or operation, in a particular time period, if all operation in the assembly line completes at its respective standard time.

For knowing about the standard time please click here. This articles explains the standard time and Time study.

Ok, lets start calculating standard output.

Suppose there is an assembly line with 4 operations A, B, C and D with standard time 7, 5, 9 and 3 minutes respectively.

First thing we need to do is to identify the bottleneck operation.

To know how to identify the bottleneck operation please click here. This article clearly explains how to identify bottleneck operation.

In this case, bottleneck operation is operation C.

And the standard time of the operation C is 9 minutes.

Now we have all the data.

Standard output can be calculated for any period of time. Here we are calculating for one shift, which has working time 420 minutes.

Standard output of assembly line = 420/9
= 46.66
And after round down it is 46 nos

Formula for calculating standard output is Working time / Standard time

We have done with the calculation.

Please have a look at below articles also. Thank You.

If you know any subject that can be related to manufacturing industry or industrial engineering, you can earn some income by becoming article contributor of this website. For knowing more about it, please visit Join us page.

You don’t need to have any experience in article writing, just knowledge on the subject is needed.

Also you can know more about our team of article contributors by visiting the about us page.

0 0 votes
Article Rating
Subscribe
Notify of
guest

0 Comments
Newest
Oldest Most Voted
Inline Feedbacks
View all comments