How To Calculate Manpower Efficiency

Suppose the total standard time for the manufacturing of a product in man minutes is 8 (Please click the highlighted words for knowing more about it). And in a shift, the assembly line of this product produces 400 nos with manpower of 11 nos. Working time per shift per manpower is 420 minutes.

Manpower efficiency = (8 x 400)/(11 x 420)
= 3200/4620
= 0.6926

In percentage it is 69.26%.

And the formula for calculating manpower efficiency in percentage is
((Standard time x no of products produced) / (working time per employee x no of employees)) x 100

This efficiency can be used for Incentive schemes, Employee appraisal and as an initiative to improvement.

Thank You for reading and supporting us.

If you know any subject that can be related to manufacturing industry or industrial engineering, you can earn some income by becoming article contributor of this website. For knowing more about it, please visit Join us page.

You don’t need to have any experience in article writing, just knowledge on the subject is needed.

Also you can know more about our team of article contributors by visiting the about us page.

Also please have a look at the following useful articles.

0 0 votes
Article Rating
Subscribe
Notify of
guest

6 Comments
Newest
Oldest Most Voted
Inline Feedbacks
View all comments
Elina Parviainen
Elina Parviainen
4 years ago

Please, remember to use the rule of ILO introduced in the book ” Introduction to work study” the same can be found from Industrial Engineering Handbooks (Salvendy, and other Maynards) well known. That is the study that combines ergonomics , human factors and the process interfaces. Engineering work that is seldom seen.

Kartik Sreedharaan
Kartik Sreedharaan
4 years ago

Hello Melvin,
thank for sharing this info. it was helpful
btw, can i know if there are any literature or reference that able to justify the above computation?
also what are your thoughts about Overall Labor Effectiveness (OLE)?

Jaya Kumar K
Jaya Kumar K
4 years ago

Now a days low cost automation or full automation determines productivity.
Synergy will increase productivity.
If maintenance work is done by a team the productivity is increased geometrically than doing the job by single person. Not only productivity, the quality increases, That is actually required above productivity.
Team work also increses safety.
I worked in Gulf The latest plant is almost fully automated and the whole system is configured throgh PLC/Distrbuted control system.
Production goes on.
There ,the nationals are sent to courses and given regular training to update the knowledge and technology.
In-house courses and training are good motivation.
Labour laws stipulates resonable wages and there is increase in skilled jobs .

Prijin
Prijin
4 years ago

This topic has very useful for me.