How to calculate savings on Machine Hour Rate

In this article I will explain how to calculate the machine hour rate you have saved by implementing some improvements in an operation of a machine.

Suppose the present output of a machine is 120 per hour. And you have done some improvement in the operation of a machine and increased the hourly output to 145, without increasing any input. So increase in the output per hour is 25 nos.

Advertisement

Machine minutes required per product before improvement = 60/120
= 0.5

Machine minutes required per product after improvement is = 60/145
= 0.4137

Machine minutes saved per product = 0.5 – 0.4137 = 0.0863

Suppose the demand of the product per month is 200000.

An anonymous founder recording a podcast in a studio, with framed Factovare and Know Industrial Engineering logos
0:00 / —:—

Machine minutes saved per month is 0.0863 x 200000 = 17260

Cost per hour of the machine is Rs 100.

Cost for one machine minute = 100/60 = Rs. 1.66

So total savings per month = 1.66 x 17260

Which is Rs. 28651/-

We are done with the calculation. Also its assumed that the machine is not idle due to no demand. If it is idle, cost for the idle time to be reduced from the calculated savings.

This calculation exactly same as we done for calculating manpower savings.

Also please have a look at the difference between 4 cycle times. Please click the link below.

Thank you for reading.

We have a Facebook page please like and share. Please click link below.

If you know any subject that can be related to manufacturing industry or industrial engineering, you can earn some income by becoming article contributor of this website. For knowing more about it, please visit Join us page.

You don’t need to have any experience in article writing, just knowledge on the subject is needed.

Also you can know more about our team of article contributors by visiting the about us page.

KIE PREMIUM

Upgrade to Premium to access complete content

Continue reading this article and enjoy the complete KIE experience.

One membership. Practical learning and resources for manufacturing professionals.

Now or Never

We’ve got your back on your manufacturing journey — Stay in touch

Follow us for step-by-step guidance, templates, and insights that save time and reduce mistakes.

Know Industrial Engineering Platform – Helping manufacturing industry professionals worldwide since 2019


Discover more from Know Industrial Engineering

Subscribe to get the latest posts sent to your email.

4 thoughts on “How to calculate savings on Machine Hour Rate”

  1. Good explanation. Hope OEE is factored in output per hour before and as well after improvement cases.Else we need to factor it to monthly savings.

Leave a Comment

Your email address will not be published. Required fields are marked *

Trainings